Project Plan

Demo 2 sprint in flight Methodology · Agile (Scrum) Sprint cadence · 2 weeks

Document overview

This document captures how the Gesture-Based Drone Control System (GBDCS) is being delivered. It is built around Agile as the methodology and Scrum as the framework.

The plan is the bridge between SRS (what we are building), SAS (how it is structured), and BRAND (what it looks like) — it answers when and in what order.


1. Methodology

1.1 Why Agile

The team adopts Agile because the problem is volatile: gesture recognition accuracy, drone-SDK behaviour, and operator expectations cannot be fully specified up front and will be discovered iteratively. The four values of the Agile Manifesto are adopted verbatim — the team values the items on the left more than the items on the right.

We value … over
Individuals and interactions Processes and tools
Working software Comprehensive documentation
Customer collaboration Contract negotiation
Responding to change Following a plan

1.2 Why Scrum on top of Agile

Within Agile, the team uses Scrum as the operating framework — fixed roles, fixed ceremonies, two-week time-boxes — because the project has hard, externally-imposed milestones (the four COS 301 demos) that benefit from short, predictable iterations.

1.3 Scrum values

The five Scrum values guide every decision the framework itself does not cover:

Commitment. The team personally commits to the goals of each sprint and to the demo it leads to.

Focus. Each sprint locks scope. Mid-sprint additions go to the backlog, never to the sprint board.

Openness. Blockers, doubts, and unknowns are surfaced in standup the day they appear.

Respect. Every team member is treated as capable and independent. No silent rewrites of someone else's work.

Courage. The team raises hard problems early, including telling the mentor when a target will slip.


2. Scrum Setup

2.1 Roles

The team's role assignments. Role boundaries are intentionally permeable — every dev contributes across the stack and to testing.

Role Member Why
Product Owner Rotates demo-to-demo; primary contact with the EPI-USE mentor Owns the backlog and priorities; agrees Definition of Done with the team.
Scrum Master + Dev Ayush Beekum Strongest integration / cross-cutting experience; removes impediments and coaches the team on the process.
Dev Team — Frontend lead Chinmayi Santhosh UI engineering and React / Tailwind background.
Dev Team — Frontend + QA Diya Narotam UI / UX, PWA, Playwright / Jest / Vitest experience.
Dev Team — DevOps & Infrastructure Jaitin Moodally Homelab / multi-OS / low-level background; owns the CI/CD pipeline, containerisation, and deployment.
Dev Team — CV & ML Shavir Vallabh TechTeam at UP, ML and HPC experience; owns the CV pipeline, recogniser strategies, and drone-adapter integration.

2.2 Ceremonies

The team runs the full Scrum ceremony set on a two-week cadence. In addition to the in-sprint ceremonies, the team meets at least twice weekly for the COS 301-mandated stand-ups (see §2.4).

flowchart LR
    P[Sprint Planning<br/>~2&nbsp;hrs · Mon&nbsp;Wk1] --> S1[Stand-ups<br/>15&nbsp;min · ≥&nbsp;2× / week]
    S1 --> BR[Backlog Refinement<br/>~1&nbsp;hr · Wed&nbsp;Wk1]
    BR --> S2[Stand-ups<br/>continue]
    S2 --> SR[Sprint Review<br/>~45&nbsp;min · Fri&nbsp;Wk2]
    SR --> RETRO[Retrospective<br/>~45&nbsp;min · Fri&nbsp;Wk2]
    RETRO -.->|next sprint| P

Figure 2.1 — The two-week Scrum cadence applied to GBDCS.

Ceremony Length Cadence Purpose
Sprint Planning ~2 hrs Monday, Week 1 Agree the sprint goal and pull stories from the product backlog into the sprint backlog.
Stand-up 15 min At least twice weekly "Yesterday / today / blockers." Minutes logged in the Group Discussion on ClickUP (see §2.4).
Backlog Refinement ~1 hr Wednesday, Week 1 Clarify, size, and split upcoming PBIs before the next planning session.
Mentor Meeting (lecturer) ~30 min Every second week Alignment on documentation, scope, and team-dynamics issues.
Sprint Review ~45 min Friday, Week 2 Demo the increment to the EPI-USE and academic mentors.
Retrospective ~45 min Friday, Week 2 What worked, what didn't, what we commit to changing next sprint.

2.3 Artifacts

Three Scrum artifacts are maintained.

  • Product Backlog — the master list of every PBI for GBDCS (see §4). Lives in the GitHub Project board.
  • Sprint Backlog — the PBIs the team has pulled into the current sprint. Tracked as GitHub Issues with the sprint-N label.
  • Burndown Chart — the open story-point total per day of the sprint (see §7).

2.4 Meeting cadence and minute-logging

The COS 301 Demo 2 brief requires the team to maintain a documented meeting cadence. The team complies as follows.

Cadence What Where logged
At least twice weekly Stand-up (15 min). "Yesterday / today / blockers" per member. Group Discussion on ClickUP for the current demo, with date, time, and attendees.
Every second week Lecturer-mentor meeting. Documentation alignment, scope, team dynamics. Group Discussion on ClickUP, with date, time, and attendees.
As needed Industry-mentor check-in with EPI-USE. Group Discussion on ClickUP, with date, time, and attendees.

The team leader is responsible for posting the minutes after every meeting. Missing minutes affect the team and individual marks per the Demo 2 brief — they are not optional.


3. Definition of Ready & Definition of Done

The Definition of Done is agreed between the team and the PO, realistic, within the team's control, short (5–8 items), well understood, and visible. Both DoR and DoD are pinned to the GitHub Project board.

A backlog item is Ready to be pulled into a sprint when:

  1. It is written in the user-story format (As a … I want … so that …).
  2. It cites at least one requirement ID from the SRS.
  3. It has at least one Given / When / Then acceptance criterion.
  4. It has been sized by the team (story-point estimate agreed).
  5. Its dependencies on other PBIs are listed.
  6. The team agrees it is small enough to complete inside one sprint (INVEST — Small).

A backlog item is Done when:

  1. All acceptance criteria pass (manual + automated).
  2. Unit tests cover the new code at ≥ 80 % line coverage (per R10.2).
  3. Code has been reviewed and merged into dev via a pull request conforming to GIT.md.
  4. CI is green on the merge commit (lint, type-check, test).
  5. The documentation site has been updated for any user-facing change.
  6. The PO (or mentor proxy) has accepted the change in the sprint review.

4. Product Backlog

The product backlog is the flat, prioritised list of every PBI for the system. PBIs are derived directly from the SRS — each maps to one or more R identifiers and to one or more use cases.

# PBI Maps to Use case First targeted demo
PBI-01 Hand tracking pipeline R3.1.*, R3.2.1 UC-1 Demo 1
PBI-02 Telemetry dashboard R1.1.3, R5.1.2 UC-2 Demo 1
PBI-03 AirSim simulator adapter R2.2 UC-3 Demo 1
PBI-04 Base features (login, themes, form validation) R16.* UC-4 Demo 1
PBI-05 Rule-based gesture recognition R3.2.2, R3.2.3 UC-1 Demo 2
PBI-06 Gesture → command translation R4.* UC-1 Demo 2
PBI-07 Real-drone adapter (Tello / xFly) R2.2, R5.* UC-1 Demo 2
PBI-08 Safety layer (idle, link loss, low battery, emergency stop) R5.2.*, R6.* UC-1, UC-2 Demo 2
PBI-09 Gesture overlay on dashboard feed R1.1.1, R1.1.2 UC-1 Demo 2
PBI-10 Command + telemetry persistence + replay R6.3 UC-5 Demo 2

PBIs targeted at Demo 3 and Demo 4 will be added to the backlog as the team approaches them. Per the Scrum value of Focus, the team is not pre-planning work beyond the next demo.

4.1 Demo 2 — 5-use-case coverage

The Demo 2 brief requires five fully integrated use cases. The mapping below shows how the active backlog satisfies that requirement. All five are existing use cases from SRS.md §4, brought to production-quality "no mocks, full integration, unit and E2E testing" status for Demo 2.

Use case New for Demo 2? Backed by
UC-1 — Control Drone via Gesture New (Demo 1 had hand tracking only; recognition + command dispatch land in Demo 2) PBI-05, PBI-06, PBI-07, PBI-08, PBI-09
UC-2 — Monitor Telemetry & Alerts Extended (Demo 1 telemetry pipe; Demo 2 adds the alert overlay + acknowledgement) PBI-08
UC-3 — AirSim Implementation Extended (Demo 1 connectivity; Demo 2 closes the loop with command dispatch) PBI-06, PBI-07
UC-4 — Authenticate Operator Session Hardened (Demo 1 login + theme; Demo 2 wires the short-lived token into the WS handshake) PBI-04 carry-over + PBI-08
UC-5 — Replay a Recorded Session New PBI-10

5. Epics & User Stories

The active backlog (PBI-05 through PBI-10) is broken down into epics, then into user stories using the standard "As a … I want … so that …" template with Given / When / Then acceptance criteria.

5.1 Epic — Gesture Recognition (PBI-05, PBI-06)

US-1 — Recognise the Open Palm gesture

Story. As an operator, I want the system to recognise an open-palm gesture so that I can command the drone to hover.

Value: 40 · Size: Medium · Maps to: R3.2.2, R4.1

Acceptance criteria.

  • Given the operator holds an open palm in view of the camera for ≥ 250 ms, when the pipeline classifies the frame, then the recognised gesture shall be OPEN_PALM.
  • Given the operator holds an ambiguous hand shape, when the classifier cannot meet the confidence threshold, then no command shall be issued (R3.2.3).
  • Given the lighting is below 200 lux, when the operator holds an open palm, then the dashboard shall surface a "low-light" warning (R11.3).

US-2 — Recognise directional pointer gestures

Story. As an operator, I want the system to distinguish pointer-left from pointer-right so that I can steer the drone horizontally.

Value: 30 · Size: Medium · Maps to: R3.2.2, R4.1

Acceptance criteria.

  • Given the operator points the index finger left, when the pipeline classifies the frame, then the recognised gesture shall be POINTER_LEFT.
  • Given the operator points the index finger right, then the recognised gesture shall be POINTER_RIGHT.
  • Given the operator holds a fist (no extended finger), then neither pointer gesture shall be reported.

5.2 Epic — Command Translation (PBI-06)

US-3 — Dispatch commands within latency budget

Story. As an operator, I want my recognised gesture to translate into a drone command within 200 ms so that the drone feels responsive.

Value: 40 · Size: Medium · Maps to: R4.3, R7.1

Acceptance criteria.

  • Given a gesture is recognised at time t, when the command translator dispatches the command, then the dispatch shall occur at t + ≤ 200 ms at the 95th percentile.
  • Given a gesture maps to the same command as the previous frame, when the translator runs, then a duplicate command shall not be re-dispatched.

5.3 Epic — Real-Drone Adapter (PBI-07)

US-4 — Plug a real drone in behind the existing interface

Story. As a maintainer, I want the real-drone adapter to satisfy the same DroneAdapter interface as the simulator adapter so that the rest of the system requires no changes.

Value: 50 · Size: Large · Maps to: R2.2

Acceptance criteria.

  • Given the active adapter is switched from airsim to tello via the environment variable, when the system is launched, then the pipeline shall connect to the physical drone with no change to any non-adapter source file.
  • Given the physical drone is unreachable, when the adapter attempts to connect, then an error shall be surfaced on the dashboard and take-off shall be refused (R6.2.2, R11.3).

5.4 Epic — Safety Layer (PBI-08)

US-5 — Hover on idle

Story. As an operator, I want the drone to hover whenever I stop gesturing so that it never drifts on its own.

Value: 50 · Size: Small · Maps to: R6.1.1

Acceptance criteria.

  • Given the drone is airborne, when no gesture is detected for more than 3 s, then the system shall issue HOVER.
  • Given the system has issued HOVER for idle, when the dashboard receives the event, then an "Idle — hovering" indicator shall be shown (R6.1.2).

US-6 — Auto-land on low battery

Story. As an operator, I want the drone to land itself when the battery drops below 15 % so that I do not have to react to it.

Value: 50 · Size: Small · Maps to: R6.2.1

Acceptance criteria.

  • Given the drone reports battery < 15 %, when the telemetry frame is received, then an auto-land sequence shall be initiated and a critical alert raised on the dashboard (R1.2.1).

US-7 — Heartbeat / link-loss hover

Story. As an operator, I want the drone to hover automatically if the link drops so that it does not fly off uncontrolled.

Value: 40 · Size: Small · Maps to: R5.2.1, R5.2.2

Acceptance criteria.

  • Given the drone adapter has sent no telemetry for > 2 s, when the heartbeat check runs, then the system shall command HOVER and surface a banner alert.

5.5 Epic — Dashboard Live View & Replay (PBI-09, PBI-10)

US-8 — Live gesture overlay

Story. As an operator, I want to see the MediaPipe skeleton drawn on the live feed so that I can tell whether the system is tracking my hand correctly.

Value: 20 · Size: Small · Maps to: R1.1.1

Acceptance criteria.

  • Given the operator's hand is in frame, when the dashboard renders the feed, then the 21 landmark points and their connecting bones shall be drawn at no less than 24 FPS.

US-9 — Persist a session for replay

Story. As a reviewer, I want every command and telemetry frame to be logged so that I can replay a session afterwards.

Value: 25 · Size: Medium · Maps to: R6.3

Acceptance criteria.

  • Given a session is active, when any command or telemetry frame is produced, then it shall be written to SQLite with an ISO-8601 timestamp.
  • Given a recorded session exists, when the reviewer triggers replay, then the dashboard shall reconstruct the original gesture and telemetry stream at original cadence (UC-5).

6. Demo Plan

6.1 Demo 1 — Foundations  Delivered

Goal Demonstrate the system skeleton: tracking + telemetry + simulator adapter + base features.
PBIs delivered PBI-01, PBI-02, PBI-03, PBI-04
Requirements satisfied R3.1.*, R3.2.1, R1.1.3, R5.1.2, R2.2, R16.*
Outcome Hand tracking, dashboard telemetry, AirSim adapter, and login / theme / validation features were demonstrated. Mentor feedback called out documentation formatting — addressed in this round of rewrites.

6.2 Demo 2 — Recognition, Real Drone, Safety, Replay  In flight

Goal Close the loop: recognise gestures, send commands to a real drone through the existing adapter interface, arm the safety layer, and demonstrate session replay — all five use cases fully integrated, no mocks.
Sprint goal A live gesture demo on real hardware with the failsafes proven on stage, plus replay of the demo run from the dashboard.
PBIs in scope PBI-05, PBI-06, PBI-07, PBI-08, PBI-09, PBI-10
Use cases brought to integration UC-1, UC-2, UC-3, UC-4, UC-5
Requirements newly satisfied R3.2.2, R3.2.3, R4.*, R5.*, R6.*, R1.1.1, R1.1.2, R1.2.*, R8.1, R8.3
Demo-level Definition of Done Drone takes off, executes at least four distinct commands from gestures, hovers on idle, hovers on link loss, lands on low battery, and the session is reviewable in replay — all on a live, publicly-accessible deployment per the SAS deployment section.

6.3 Demos 3 & 4  To be planned

Per the Scrum value of Focus, the team is not pre-planning these. Backlog refinement at the end of the Demo 2 sprint will surface the Demo 3 PBIs from the SRS requirements that are not yet satisfied — chiefly the R7.* performance bar, the R9.* reliability bar, and the R11.* usability targets. Demo 4 will be planned at the close of Demo 3 in the same way.


7. Burndown & Velocity

Two charts are tracked across the project.

7.1 Sprint burndown (Demo 2 sprint, current)

xychart-beta
    title "Demo 2 sprint — burndown"
    x-axis ["D1","D2","D3","D4","D5","D6","D7","D8","D9","D10"]
    y-axis "Open story points" 0 --> 50
    line [50, 45, 45, 40, 36, 30, 26, 20, 12, 0]

Figure 7.1 — Burndown for the current Demo 2 sprint. The straight line from 50 → 0 over 10 working days is the ideal trajectory; the team's actual line is plotted against it. Updated daily at stand-up.

7.2 Velocity (story points per sprint)

xychart-beta
    title "Velocity per sprint"
    x-axis ["Sprint 1<br/>(Demo 1)","Sprint 2<br/>(Demo 2 wk 1-2)"]
    y-axis "Story points delivered" 0 --> 60
    bar [42, 0]

Figure 7.2 — Velocity after Sprint 1 (Demo 1). Sprint 2 closes at the end of the current cadence; the bar will be filled at the sprint review. Velocity will guide commitment in subsequent sprints — the team will not pull more story points into a sprint than the rolling average.

Live updates

These charts are illustrative snapshots committed to the repo. The live burndown and velocity for each sprint are tracked on the GitHub Project board and updated at every stand-up and sprint review.


8. Blockers & Mitigations

# Blocker Status Mitigation
B1 Real-drone SDK behaviour (xFly / Tello) differs from AirSim Tracking Adapter parity tests; vendor support thread open; DummyDroneAdapter covers offline development.
B2 Telemetry-format divergence between AirSim and physical drone Tracking Shared TelemetryFrame schema in packages/contracts; per-adapter translators map vendor payloads to the schema.
B3 Latency variability under load Tracking Bounded-queue pipeline (see SAS §2.1); CPU profile in CI; latency harness planned for Demo 3.
B4 Cloud-deployment provisioning not yet complete Tracking Render account being wired up during the Demo 2 sprint; local Docker-Compose path covers all dev and integration testing in the interim (see SAS §5.3).
B5 Time-zone overlap for joint mentor reviews Resolved Sprint Review scheduled in a window that suits both mentors.

The Scrum Master logs every new impediment in the project board as it surfaces in stand-up.


9. Buzzword Reference (GBDCS-specific)

A short reference of the terms used in this document, mapped to how they apply on GBDCS.

Term Definition What it looks like on GBDCS
PBI Product Backlog Item A row in §4.
Epic A large PBI broken into smaller stories Each subsection of §5.
User Story "As a … I want … so that …" The !!! example blocks in §5.
AC Given / When / Then conditions The bullets inside each user story.
DoR / DoD Definition of Ready / Definition of Done §3.
Sprint Fixed 2-week time-box The cadence in §2.2.
Velocity Story points completed per sprint §7.2.
Story Points Relative effort estimate The "Size" field on each user story (Small / Medium / Large).
Impediment Anything blocking team progress An entry in §8.
MVP Smallest thing that delivers real value Demo 1 — hand tracking + telemetry + simulator.
INVEST Independent · Negotiable · Valuable · Estimable · Small · Testable Each story in §5 is checked against this before becoming Ready.